How to import Version 6.0.0 XER file to Contractor 5.0?

Niyaaz AlikhanMember for 18 years 8 months
Created
1
2
0
I need to import an 6.0.0 XER file to Contractor 5.0. I tried and received an error message that said "A version 6.0.0 XER file cannot be imported." Could someone please help me. Thank youl.

1 reply

Oldest first
  1. 0
    K D ·
    Hi Niyaaz.
    You can not import 6.0 XER to 5.0.
    There’s a solution in Primavera website POINT.
    Solution ID : prim51081
    Regards