Budget distribution in Recovery Programme
In the Open Standard
Kannan CPMember for 18 years 4 months
- Created
- 6
- 6
0
HI,
I made a recovery programme, developed from the latest update of the approved baseline programme. Budget is loaded in the programme. In the activity spreadsheet of the recovery schedule, the budget seems to be distributed not as per the dates. Many activites have budget distribution even after the completion date.
In the activity spread sheet, I used the Budgeted Total Cost to see the budget distribution.
Is there any reason for it?
Thanks and Regards
Kannan
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?