Copy one column of a project to another??

Arun KumarMember for 18 years 6 months
Created
5
2
0
I have two different project in P5.Now I want copy one complete column of one project to another project or i want to use the same column in both project .

Can anyone help me??

Arun

5 replies

Oldest first
  1. 0
    Andrew Dick ·
    Arun,
    If the column is a code field then it should be possible if the activity code is set as either a global or EPS code.

    Not knowing what type of data you wish to use could you provide more info?

    It could be just a matter of ensuring that the column is displayed by slecting it in a common layout.

    Give us a bit more to go on.

    Andy
  2. 0
    Arun Kumar ·

    Dear Andy

    column is not a code field.Its just a text field.How can it be displayed in common layout & used for other project also?

    Arun
  3. 0
    Shiv Rao ·
    Can you clarify with what you actually want.

    give specific examples and then i think we can help you .


    like you want to copy a set of BL1 finish dates from one project to other ?

    Shiv
  4. 0
    Dang Corp ·
    Hi Arun,

    i know what u mean,

    You wanted:
    ================
    to copy UDF (user defined fields) of text UDF
    from PROJECT 1,,, to project 2.

    Answer:
    ================
    No, u can’t do it in Primavera.
    even global change can’t do at PROJECT LEVEL.


    OTHER OPTIONS
    =================
    One:
    ---
    learn the Primavera SDK or API
    (if you have not heard of SDK or API) call up the Primavera for assistant.

    Two:
    ---
    go to this website and download the software and it does what u r after.

    www.dangcorp.com/toolbox.aspx


    Vu Dang






  5. 0
    Arun Kumar ·
    ya this is what i wanted..

    its not possible in Primavera.


    ok...