Plan% Column
In the Open Standard
Izam ZakariaMember for 20 years 4 months
- Created
- 2
- 1
0
Hi Mates,
As subjected above, I try to come out one column for Plan % figure (for every single activity)
What I did as following below:-
If
Where Early start is less than 19-Nov-09 (as cut-off date)
And Activity Type equals Task Dependent
Then
User_interger3 = user_start_date5 – BL1 Start
User_interger3 = User_interger3 / BL Project Duration
User_interger3 = User_interger3 * 100
User_interger1 = user_integer3
But the result is too disappointed. Is it anyone can do me favour?
Thx and have a nice weekend
2 replies
Oldest firstLog in or join to reply