Plan% Column

Izam ZakariaMember for 20 years 4 months
Created
2
1
0

Hi Mates,

As subjected above, I try to come out one column for Plan % figure (for every single activity)
What I did as following below:-

If
Where Early start is less than 19-Nov-09 (as cut-off date)
And Activity Type equals Task Dependent

Then
User_interger3 = user_start_date5 – BL1 Start
User_interger3 = User_interger3 / BL Project Duration
User_interger3 = User_interger3 * 100
User_interger1 = user_integer3

But the result is too disappointed. Is it anyone can do me favour?

Thx and have a nice weekend


2 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Izam,

    With P6, you don’t need to perform a global change to show the Plan %, you can simply display the column of Schedule % Complete as long as you have the baseline assign to your current schedule.

    Regards,

    Arnold
  2. 0
    Izam Zakaria ·
    Hi Arnold,

    Thanks man, thanks for the guidance :)