Project Baseline & Primary Baseline

Suresh Sankarankutty PMPMember for 20 years 2 months
Created
1
3
0
Hi
Could you please tell the main difference between Project baseline and primary baseline. What is the use of both and what circumstance or when would we use for what ???

Would be appreciated if you could give some example.


Regards
Suresh

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Suresh,
    project baseline can be seen by any user who has rights on the project; primary (and secondary, tertiary baselines too) can only be seen by the user who saved them
    of course, if you are using a standalone PM5/6, you will not have any difference
    Alexandre