Planned Dates = Start and Finish Dates

Richard HillMember for 20 years 4 months
Created
1
1
0
Global Change in P6 is not as easy as it used to be (i.e. in P3)

For the life of me I can’t seem to get the parameters to say - Planned Start = Start and Planned Finish = Finish. I mean, come on the logic is simple enough then why can’t I find any parameter to say just that!

Thanks

1 reply

Oldest first
  1. 0
    Richard Hill ·
    Apologies no need for reply back.
    I figured it out in the end! Wasn’t what I expected but I entererd
    Start is Greater than or Equal to PS and
    Finish is Less than or eEqual to PF
    > Then Planned Start is Equal to Start and
    Planned Finish is Equal to Finish.