P6 Calculating Earned Value
In the Open Standard
Omar GrantMember for 21 years
- Created
- 1
- 1
0
I have a schedule with resources applied to activities with percentage type = physical. I also have weighted steps on each activity. When I update the steps I get a calculated % complete against the activity OK but, unless the activity steps are all 100% I do not get a value for Earned Value Labour Units. I have checked all the preferences & calculation tabs to no avail. Can anyone help please?