P6 Calculating Earned Value

Omar GrantMember for 21 years
Created
1
1
0
I have a schedule with resources applied to activities with percentage type = physical. I also have weighted steps on each activity. When I update the steps I get a calculated % complete against the activity OK but, unless the activity steps are all 100% I do not get a value for Earned Value Labour Units. I have checked all the preferences & calculation tabs to no avail. Can anyone help please?

1 reply

Oldest first
  1. 0
    Anoon Iimos ·
    Omar,

    Physical % progress is manually calculated (or you input manually) so you need to calculate earned value manually as well.

    cheers

Log in or join to reply