How to create Cumulative Late Curve in P6
- Created
- 129
- 8
In P3, there is an easy step under tool (report tool) to display both of them, but in P6 where???
Or could you teach me how I can extract cost loading data based on late start date into excel? Then I can generate a cumulative late curve.
Thanks in advance.
129 replies
Oldest first- 0JJJohn Jacob ·
Hi Arnold, Admit I am very
Hi Arnold,
Admit I am very late in tihis forum. But much appreciate if you could send me the late and early curve generation techniques.
My email is jjacobjp@yahoo.com
Many Thanks.
John.
- 0JJJohn Jacob ·
Hi Arnold, Admit I am very
Hi Arnold,
Admit I am very late in this forum. But much appreciate if you could send me the late and early curve generation techniques.
My email is jjacobjp@yahoo.com
Many Thanks.
John.
- 0RDRafael Davila ·
Just remember you will need
Just remember you will need two sets of early and late S curves (two banana curves). One for the baseline schedule and another for the current schedule that shall not only display actual performance up to data date but also shall display projected early and late S curves after data date.
Also remember to apply postings to financial periods if your software is not capable of display correct values without using periods, an unneeded patch in more capable software. At least P6 is better than SureTrak that was not able to display correct values and did not provided such patch. P6 requires such patch same as P3 but at least P6 allows you to edit closed periods while P3 does not. The BUG has to do with the design of the mathematical distribution of activities that span performance over two updating periods, for most people the way around using financial periods is ok.
- 0
- 0
- 0AEAngelito Estrella ·
good day arnold, this may a
good day arnold,
this may a bit late
still, please could you send me the steps
iam new in p6
appreciate your help
my eadd; amestrella25@yahoo.com
- 0CCChristian Chandler ·
Hi Arnold, Would you please
- 0CCChristian Chandler ·
Hi Arnold, Would you please
Hi Arnold,
Would you please send me the details also; christian.chandler@riotinto.com.
Cheers
Christian - 0RDRafael Davila ·
I do not use P6 but using
I do not use P6 but using Google found the following link that shows a way to generate the data for Excel, then with a knowledge of Excel or using an Excel template you can generate the combined curves.
http://primaverarena.com/wp-content/uploads/2010/05/S-curve-creation-for-P6.pdf
The following links provides some tutorials that might be of interest and perhaps showing a different approach.
http://www.toolboxforplanning.com/p/tutorials.html
http://www.toolboxforplanning.com/2010/10/excel-2003-tutorial-creating-progress-s_16.html
You can download their template or a modified version I just created to include early and late banana curves from the following link.
http://www.mediafire.com/download.php?ekc33bya2nd44e4
I prefer to display on the vertical axis the absolute values instead of percentages as it can create confusion when contract value changes.
Because of the way P6 stores period performance on uncompleted activities there can be discrepancies on displayed period performance if you do not make use of financial periods. The following link can provide you with an introduction on this issue.
http://primaverablog.in/2011/03/financial-periods-2/
Hope this help.
Regards,
Rafael
- 0DJDwi Jaka Prastya ·
Hi Mr Arnold can you send me
Hi Mr Arnold
can you send me also
prastya.dj@gmail.com
Thanks - 0SBSunil Babu ·
Hi Arnold, pls send me
Hi Arnold,
pls send me also..(s -curve late and early)
mail: sb_sunil2000@yahoo.com
Thanks in advance
Sunil.
- 0AJArshad Jamil ·
Hi Arnold, Please, also send
Hi Arnold,
Please, also send me the steps on how to create the comulative late curve in P6.
This is my email : jamil_arshad@rediffmail.comThanks & Regards
jamil
- 0KSKhaja Sharief ·
Early & late curves can be
Early & late curves can be generated straight away once you have resources loaded schedule in P6.
You can find these curves ready made for you in activity usage profile window. Right click on the graph and select At activity usage profile options. Under Bar/curves, select Remaining Early or Remaining late curve.
Cheers...
- 0MSMohammed Siraj ·
Hi Arnold,Please share with
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?