How to create Cumulative Late Curve in P6

Paul YoonMember for 22 years 1 month
Created
129
8
0
I am trying to find out how to generate a cumulative Late Curve and cumulative early curve for my cost loading/cash flow in P6. However I still don’t know how to do it.

In P3, there is an easy step under tool (report tool) to display both of them, but in P6 where???

Or could you teach me how I can extract cost loading data based on late start date into excel? Then I can generate a cumulative late curve.
Thanks in advance.

129 replies

Oldest first
  1. 0
    John Jacob ·

    Hi Arnold,   Admit I am very

    Hi Arnold,

     

    Admit I am very late in tihis forum. But much appreciate if you could send me the late and early curve generation techniques.

    My email is jjacobjp@yahoo.com

    Many Thanks.

    John.

  2. 0
    John Jacob ·

    Hi Arnold,   Admit I am very

    Hi Arnold,

     

    Admit I am very late in this forum. But much appreciate if you could send me the late and early curve generation techniques.

    My email is jjacobjp@yahoo.com

    Many Thanks.

    John.

  3. 0
    Irfan Khan ·

    pls send me here

    pls send me here irfan_kn2006@hotmil.com

     

    i will be thankful ..........

     

     

     

  4. 0
    Rafael Davila ·

    Just remember you will need

    Just remember you will need two sets of early and late S curves (two banana curves). One for the baseline schedule and another for the current schedule that shall not only display actual performance up to data date but also shall display projected early and late S curves after data date.

    S Curves

    Also remember to apply postings to financial periods if your software is not capable of display correct values without using periods, an unneeded patch in more capable software. At least P6 is better than SureTrak that was not able to display correct values and did not provided such patch. P6 requires such patch same as P3 but at least P6 allows you to edit closed periods while P3 does not. The BUG has to do with the design of the mathematical distribution of activities that span performance over two updating periods, for most people the way around using financial periods is ok.

  5. 0
    John Rovir Fernandez ·

    Hi Arnold, Can you kindly

    Hi Arnold,

     

    Can you kindly send it to me as well. please.  jrrfernandez@yahoo.com

    Thank you.

     

    JRF

  6. 0
    Inas Atef ·

    hi can u send me

    hi

    can u send me also
     stars.light@live.com

     

    best regards.

  7. 0
    Ayman Eleish ·

    Dear All, That can be done

    Dear All,

    That can be done from the Assignment screen to copy the resorces usage and to paste in excel sheet.

    Regards,

  8. 0
    Ali Ahmad ·

    me too, really need it

    me too, really need it   cat56456@yahoo.com

  9. 0
    Angelito Estrella ·

    good day arnold, this may a

    good day arnold,

    this may a bit late

    still, please could you send me the steps

    iam new in p6

    appreciate your help

    my eadd; amestrella25@yahoo.com

  10. 0
    German Rogers ·

    Hi Arnold, may I request you

    Hi Arnold, may I request you a copy of the instructions about how to create the cumulative curve?

    I will be thankful.

    My email address is:  germanrogers@gmail.com

    Thanks,

    German.

     

  11. 0
    Christian Chandler ·

    Hi Arnold,   Would you please

    Hi Arnold,

     

    Would you please send me the details also; christian.chandler@riotinto.com.

     

    Cheers

  12. 0
    Christian Chandler ·

    Hi Arnold,   Would you please

    Hi Arnold,

     

    Would you please send me the details also; christian.chandler@riotinto.com.

     

    Cheers

    Christian
  13. 0
    J Martin ·

    Arnold will you please send

    Arnold will you please send me the steps? wonjmartin@hotmail.com

    Thank you

  14. 0
    Jaime Sax Maliwat ·

    Hey Guys,Could please send me

    Hey Guys,

    Could please send me the procedure?Thanks!email: j.maliwat@yahoo.com

  15. 0
    Imran Rana ·

    can u send me to

    can u send me to rana.imran@hotmail.com

  16. 0
    Ashraf El Sharkawi ·

    can you please send me the

    can you please send me the steps and the required software( or plugin) to be able to generate these curves?

    ashraf_shoukry_5@hotmail.com

  17. 0
    Ashraf El Sharkawi ·

    can you please send me the

    can you please send me the steps and the required software( or plugin) to be able to generate these curves?

    ashraf_shoukry_5@hotmail.com

  18. 0
    Rafael Davila ·

    I do not use P6 but using

    I do not use P6 but using Google found the following link that shows a way to generate the data for Excel, then with a knowledge of Excel or using an Excel template you can generate the combined curves.

    http://primaverarena.com/wp-content/uploads/2010/05/S-curve-creation-for-P6.pdf

    The following links provides some tutorials that might be of interest and perhaps showing a different approach.

    http://www.toolboxforplanning.com/p/tutorials.html

    http://www.toolboxforplanning.com/2010/10/excel-2003-tutorial-creating-progress-s_16.html

    You can download their template or a modified version I just created to include early and late banana curves from the following link.

    http://www.mediafire.com/download.php?ekc33bya2nd44e4 

    Photobucket

    I prefer to display on the vertical axis the absolute values instead of percentages as it can create confusion when contract value changes.

    Because of the way P6 stores period performance on uncompleted activities there can be discrepancies on displayed period performance if you do not make use of financial periods. The following link can provide you with an introduction on this issue.

    http://primaverablog.in/2011/03/financial-periods-2/

    Hope this help.

    Regards,

    Rafael

  19. 0
    Badrul Helmi ·

    Arnold, send to me

    Arnold, send to me too..

    bentonitecement@yahoo.com.my

     

    tqvm

  20. 0
    Dwi Jaka Prastya ·

    Hi Mr Arnold can you send me

    Hi Mr Arnold

    can you send me also

    prastya.dj@gmail.com

    Thanks

  21. 0
    Tariq Amine ·

    hi, I'm new in this forum & I

    hi, I'm new in this forum & I ask you to teach me how to create a s-urve conjugated with global change ??? thank you.

  22. 0
    Sunil Babu ·

    Hi Arnold, pls send me

    Hi Arnold,

    pls send me also..(s -curve late and early)

    mail: sb_sunil2000@yahoo.com

    Thanks in advance

    Sunil.

  23. 0
    Arshad Jamil ·

    Hi Arnold, Please, also send

    Hi Arnold,

    Please, also send me the steps on how to create the comulative late curve in P6.
    This is my email :          jamil_arshad@rediffmail.com

    Thanks & Regards

    jamil

  24. 0
    Khaja Sharief ·

    Early & late curves can be

    Early & late curves can be generated straight away once you have resources loaded schedule in P6.

    You can find these curves ready made for you in activity usage profile window.  Right click on the graph and select At activity usage profile options. Under Bar/curves, select Remaining Early or Remaining late curve.

    Cheers...

  25. 0
    Karim Ragab ·

    Hi Arnold, Please, also send

    Hi Arnold,

    Please, also send me the steps on how to create the comulative late curve in P6.
    This is my email :  karimrgb@hotmail.com

    Thanks & Regards

    karim

  26. 0
    Mohammed Siraj ·

    Hi Arnold,Please share with

    Hi Arnold,

    Please share with me the steps.

    My email is siraj2000@sify.com

    Regards,

    Siraj

  27. 0
    Saida Njim ·

    Hi Arnold Please send this

    Hi Arnold

     

    Please send this document in my mail : fcs.btp@topnet.tn

     

    Thank you very much

  28. 0
    Rajeev Kumar ·

    Hi , Please send me the steps

    Hi , Please send me the steps for creating  late curve and early curve. Thanks, Rajeev

  29. 0
    Zoltan Palffy ·

    there is no link just go to

    there is no link just go to view show on bottom resource usage profile and select either the early or late dates

    view show on bottom resource usage profile then select 

    remaining early and or remaining late