How to create Cumulative Late Curve in P6
- Created
- 129
- 7
In P3, there is an easy step under tool (report tool) to display both of them, but in P6 where???
Or could you teach me how I can extract cost loading data based on late start date into excel? Then I can generate a cumulative late curve.
Thanks in advance.
129 replies
Oldest first- 0MPMark Porter ·Hi Arnold,
Way back at post # 2 you stated that you must create two baselines & attach to the project, these baselines are as follows;
1. Baseline (Early Planned) - Project Baseline
2. Late Planned - Users Primary Baseline (BL1)
I was kindly wondering how you are creating your late baseline?
Currently, I run a Global Change to match the start / finish dates to the late dates, but the only other way that I can think of getting the late dates is by assigning "As late as possible" constraints & scheduling accordingly...
Do you know of any settings that allows you to schedule the program based on the late dates, or do you know of a easier way that I may not know of?
Kind Regards
Mark Porter - 0WLwalid Lahiani ·
Good morning arnold, Could
- 0CZCesar Zacarias Vistal ·
Hai, Arnold, can you post
Hai,
Arnold, can you post me also the steps on below mail:
Thanks very much.
Cesar
- 0PSPat Smith ·
Arnold, Please forward steps:
- 0MAMuhammad Aqeel ·
Hi Arnold,Can u send me also
Thanks & Kind regards, - 0WMWaheed Mirza ·
Hi .you can produce "s" curve
Hi .you can produce "s" curve in p6 only when you had assign budgeted value to activities.if you have then.go to "report "left side toolbar click on reports go to Reports group-Cost then Report group tabular then right click on monthly project cash flow.click run -report select ASCII text file then click ok.excel file will open showing cashflow.monthly and cummulative -month wise.now u are ready with data to produce s curve using excel chart.
- 0AEAyman Eleish ·
Hi Arnold,Please, also send
Hi Arnold,
Please, also send me the steps on how to create the comulative late curve in P6.
This is my e-mail..ayman_eleish@hotmail.com - 0KJKannan Jaishankar ·
Hi Arnold & Others, Can you
Hi Arnold & Others,
Can you please Send me the steps to be followed to create S- Curves for Both Early and Late dates.
My e-mail id is kannan_Jaishankar@yahoo.co.in.
Thanks in advance
- 0AAAlaa Al haj ·
i Appreciate if anyone send
i Appreciate if anyone send copy to me
- 0AAAlaa Al haj ·
i Appreciate if anyone send
i Appreciate if anyone send copy to me
- 0SKSaule Kokeyeva ·
Arnold, Please send those