How to create Cumulative Late Curve in P6

Paul YoonMember for 22 years 1 month
Created
129
7
0
I am trying to find out how to generate a cumulative Late Curve and cumulative early curve for my cost loading/cash flow in P6. However I still don’t know how to do it.

In P3, there is an easy step under tool (report tool) to display both of them, but in P6 where???

Or could you teach me how I can extract cost loading data based on late start date into excel? Then I can generate a cumulative late curve.
Thanks in advance.

129 replies

Oldest first
  1. 0
    Scarllet Pimpernel ·
    Dear Arnold,

    Please send me:

    ellenedar@yahoo.com

    Many thanks
    Scarllet
  2. 0
    Abbas India ·
    Dear Arnold,

    Please send me as well.

    thiru_abbas@yahoo.com

    Many thanks
    Abbas.
  3. 0
    Forat Faris ·
    Hi

    can you send it also to foratfaris@maktoob.com

    Thanx in advance!
    forat
  4. 0
    Ghassan Zihri ·
    Hi Arnold,

    can you send me the same to gzihri@yahoo.com?

    thanks & regards,
    ghassan
  5. 0
    Wungyea Lee ·
    Hi! Arnold,
    In digging past forum posts I have found this topic, would you mind e-mail me the step by step guide in create the said ?
    my e-mail is wungyea@mail.nsysu.edu.tw
    thank you in advance!





    Lee Wungyea
  6. 0
    Arnold Puy ·
    Hi Guys,

    Already sent.

  7. 0
    Francis Moyalan, PMP,PMI-SP ·
    Hi Arnold,

    I am late comer to this forum, if you don’t mind please send me the details to my e mail id-

    francis34@rediffmail.com

    Cheers

    Francis M Varghese
  8. 0
    Arnold Puy ·
    Guys,

    Already sent.

  9. 0
    Mujaffer Shaikh ·
    Sir Arnold ,
    Can you please forward me at ( mujaffer.shaikh@gmail.com ) as well the steps for generating cumulative late curve.

    Thanks & regards

    Mujaffer
  10. 0
    Roldan Bartolome ·
    Arnold,

    can you send also to my e-mail add; rgbart2@yahoo.com

    Thanks & regards


  11. 0
    Tandyo Winarno ·
    Hi Arnold,

    I also late for joining this topic. Would you please send the step to me to my email as follows:

    tandyow@yahoo.com


    Thanks and regards,
    Tandyo
  12. 0
    Arnold Puy ·
    Hi Guys,

    Already sent.

  13. 0
    Willem Viljoen ·
    Hi Arnold,

    Would you mind sending me the steps as well.

    wviljoen@ananzi.co.za

    Thank you.

    Willem.
  14. 0
    pat Gatus ·


    Hi Arnold,

    i am just a beginner in P6 and i would very much appreciate if you please send me the steps also

    thanks & regards,

    Pat

    My email add is uangbo08@yahoo.com
  15. 0
    Jun Partoriza ·
    Can u send me also the procedure to my email ad:
    jford_dmx@yahoo.com.

    Thanks.
  16. 0
    Arnold Puy ·
    Guys,

    Already sent.

  17. 0
    Abbas India ·
    Hi Arnold,

    Can u send me also the procedure to my email ad:

    saidumd@gmail.com

    Thanks.
  18. 0
    Mina Arsal ·
    Hi Arnold,

    Can u send me the procedure to my email:

    mina.arsal@gmail.com

    Thanks in advance.
  19. 0
    Mark Porter ·
    Hi Arnold,

    Way back at post # 2 you stated that you must create two baselines & attach to the project, these baselines are as follows;

    1. Baseline (Early Planned) - Project Baseline
    2. Late Planned - Users Primary Baseline (BL1)

    I was kindly wondering how you are creating your late baseline?

    Currently, I run a Global Change to match the start / finish dates to the late dates, but the only other way that I can think of getting the late dates is by assigning "As late as possible" constraints & scheduling accordingly...

    Do you know of any settings that allows you to schedule the program based on the late dates, or do you know of a easier way that I may not know of?

    Kind Regards

    Mark Porter
  20. 0
    Ramzi AGOUDJIL ·

    Dear Arnold, Please send

    Dear Arnold,

    Please send me:

    agoudjilramzi@gmail.com

    Thnx.

    Ramzi

  21. 0
    Anthony Delmiguez ·

    Hi Arnold! Can you share the

    Hi Arnold! Can you share the steps also? My e-mail address is LSSAPD@YAHOO.COM I'm a new member. Best regards!
  22. 0
    walid Lahiani ·

    Good morning arnold, Could

     

    Good morning arnold,

    Could you send me the file ?     walid_lahiani@hotmail.fr

     

    Thank you

  23. 0
    Cesar Zacarias Vistal ·

    Hai,   Arnold, can you post

    Hai,

     

    Arnold, can you post me also the steps on below mail:

    cesar_zacarias@orascomci.com

    Thanks very much.

     

    Cesar

  24. 0
    Pat Smith ·

    Arnold, Please forward steps:

    Arnold,

    Please forward steps: rcktfanatic34@yahoo.com

    Thanks!!

  25. 0
    Y Malik ·

    Hi Arnold,Can you please send

    Hi Arnold,

    Can you please send me the steps at younus@ualberta.ca

    Thanks,

    Malik

  26. 0
    Muhammad Aqeel ·

    Hi Arnold,Can u send me also

    Hi Arnold,

    Can u send me also the procedure to my email ad:

    maqeel2008@hotmail.com
     
    Thanks & Kind regards,
  27. 0
    Waheed Mirza ·

    Hi .you can produce "s" curve

    Hi .you can produce "s" curve in p6 only when you had assign budgeted value to activities.if you have then.go to "report "left side toolbar click on reports go to Reports group-Cost then Report group tabular then right click on monthly project cash flow.click run -report select ASCII text file then click ok.excel file will open showing cashflow.monthly and cummulative -month wise.now u are ready with data to produce s curve using excel chart.

  28. 0
    Ayman Eleish ·

    Hi Arnold,Please, also send

    Hi Arnold,

    Please, also send me the steps on how to create the comulative late curve in P6.
    This is my e-mail..ayman_eleish@hotmail.com

  29. 0
    Irfan Khan ·

    Hi, Pls send me copy here :

    Hi,

     

    Pls send me copy here : irfan_kn2006@hotmail.com

     

    thanks

  30. 0
    Jorge Taguinod ·

    I did one just a couple of

    I did one just a couple of months ago.  Note that your schedule should not have any updates yet.  Then follow Karim Maghob's recommendation.  It shoudn't be rocket science.

  31. 0
    Jorge Taguinod ·

    I did one just a couple of

    I did one just a couple of months ago.  Note that your schedule should not have any updates yet.  Then follow Karim Maghob's recommendation.  It shoudn't be rocket science.

  32. 0
    DM Rabello ·

    Olá Arnold can you send me

    Olá Arnold

    can you send me also 

    enex@terra.com.br

    Thanks

     

    Rabello from Brazil

  33. 0
    DM Rabello ·

    Olá Arnold can you send me

    Olá Arnold

    can you send me also 

    enex@terra.com.br

    Thanks

     

    Rabello from Brazil

  34. 0
    Kannan Jaishankar ·

    Hi Arnold & Others,   Can you

    Hi Arnold & Others,

     

    Can you please Send me the steps to be followed to create S- Curves for Both Early and Late dates.

    My e-mail id is kannan_Jaishankar@yahoo.co.in.

     

    Thanks in advance

  35. 0
    Bert Ella ·

    i agree to the suggestion of

    i agree to the suggestion of Mr. Waheed Mirza.

    just try it. it's easy.

     

    more power Planners!

  36. 0
    Alaa Al haj ·

    i Appreciate if anyone send

    i Appreciate if anyone send copy to me

    aalhaj@ccc.ae

  37. 0
    Alaa Al haj ·

    i Appreciate if anyone send

    i Appreciate if anyone send copy to me

    aalhaj@ccc.ae

  38. 0
    Eddy San Gabriel ·

    this is a bit late for a

    this is a bit late for a request, please also send me this exercise.. thanks

  39. 0
    Dindima Manjunatha ·

    Hi Arnold, Please, also send

    Hi Arnold,

    Please, also send me the steps on how to create the comulative late curve in P6.
    This is my email :dindima83@gmail.com

    Thanks & Regards

    Dindima.

  40. 0
    Emee Del Mundo ·

    Hi Mark, Can you help me how

    Hi Mark,

    Can you help me how to use Global change? Can you give me a procedure how to change duration % to physical % using global change...

    Thanks.

    Emee

  41. 0
    Emee Del Mundo ·

    Hi Mark, Can you help me how

    Hi Mark,

    Can you help me how to use Global change? Can you give me a procedure how to change duration % to physical % using global change...

    Thanks.

    Emee

  42. 0
    Leoncio III Asilom ·

    Hi Arnold Can you post your

    Hi Arnold

     

    Can you post your steps in this forum so that everybody can see 

    cuz the forum is full of email request 

     

     

    Thanks

     

    Leo

  43. 0
    Saule Kokeyeva ·

    Arnold,   Please send those

    Arnold,

     

    Please send those details to me saule_kokeyeva@mail.ru

     

    Regards,

     

    Saule

  44. 0
    Samer Salma ·

    Hi Arnold,Please send it to

    Hi Arnold,

    Please send it to me also

    My email is: saas70@gmail.com

     

    Thanks

    Samer

  45. 0
    Mohamed Fawzy ·

    hey can you send me the steps

    hey can you send me the steps of how i do the early and late cumaltive cash flow for cost and time for the whole project, please send me the steps at    lost_enigma666@hotmail.com       thanks alot

  46. 0
    Mohamed Fawzy ·

    heycan you send me the steps

    hey

    can you send me the steps for doing the early and the late cumaltive curves on P6,please send it to my email

    lost_enigma666@hotmail.com    thanks

  47. 0
    Shalabh Gupta ·

    Hey All i NEED TO GENERATE

    Hey All

     

    i NEED TO GENERATE FINANCIAL S-CURVE FROM P-6, HOW TO DO IT? CAN ANYONE EXPLAIN.

    PERCENTAGE PHYSICAL PROGRESS CALCULATION?

  48. 0
    Shalabh Gupta ·

    Hey All i NEED TO GENERATE

    Hey All

     

    i NEED TO GENERATE FINANCIAL S-CURVE FROM P-6, HOW TO DO IT? CAN ANYONE EXPLAIN.

    PERCENTAGE PHYSICAL PROGRESS CALCULATION?

  49. 0
    Shalabh Gupta ·

    Hey All i NEED TO GENERATE

    Hey All

     

    i NEED TO GENERATE FINANCIAL S-CURVE FROM P-6, HOW TO DO IT? CAN ANYONE EXPLAIN.

    PERCENTAGE PHYSICAL PROGRESS CALCULATION?

  50. 0
    dulat Praliyev ·

    Hey all Can you send detial

    Hey all

     

    Can you send detial as well??

Log in or join to reply