PROJECT FINISHED DATE NOT CHANGING.

Shahzad AhmadMember for 18 years 8 months
Created
2
2
0
HI -ALL

I AM UPDATING MY PROJECT SCHED.IN P6

SOME ACTIVITY HAS STARTED BEFORE TIME.

WHER I HAVE GIVE THEM START DATE AND % COMPLT. REMAINING DURATION ETC..

HOWEVER AFTER PRESS F9 PROJECT FINSHED DATE STILL SAME AS BL SCHED.

THANKS FOR ADVISE.


2 replies

Oldest first
  1. 0
    Diego Henriquez ·
    Hi Shazad

    Your project completion date will only change if an activity in the critical path changes.
    You can have a delivery or future event dictating the completion date of your project, and if so, you can commence all the activities aerlier that you want to, but the critical path will remain unchanged.
  2. 0
    Shahzad Ahmad ·
    Hello Mr.Diego

    Thanks for your reply.

    This is valid reply from you in my schedule all updated activity are not critical thats why finished date of project not reflecting.


    Best Regards

    Shahzad