Skip to content

import pct to p6

Johnny WeeMember for 19 years 2 months
Created
2
1
0
hi all

i am trying to learn importing excel file to p6

i notice that i cannot import duration percent complete without modifying its remaining duration also, what is the best way to update using excel? or maybe i’m missing one important point.

hope somebody can help.

thanx

2 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Johnny,

    You cannot modify, change and edit in Excel all columns title having the symbol of (*). If you want to change your duration % complete, you need to change your remaining duration and put the actual start.

    The only workaround is to create a UDF and export to excel then create global change.

    HTH.

    Regards,

    Arnold
  2. 0
    Johnny Wee ·
    thanx

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?