Probelms in report
In the Open Standard
Mas JoeMember for 17 years 5 months
- Created
- 1
- 1
0
Hello Expert planners
I need help in resolving the problem in reports.
when I am schedule my project in P6 end date say sept 2009. I assign my BOQ values as non labour units. If run a report for cash flow in & units my end date shows as sept 2019.My planned dates of resource & activity are not same. I want to know what could be the possible reason & how to resolve this problem
I need help in resolving the problem in reports.
when I am schedule my project in P6 end date say sept 2009. I assign my BOQ values as non labour units. If run a report for cash flow in & units my end date shows as sept 2019.My planned dates of resource & activity are not same. I want to know what could be the possible reason & how to resolve this problem
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?