Hello Expert planners
I need help in resolving the problem in reports.
when I am schedule my project in P6 end date say sept 2009. I assign my BOQ values as non labour units. If run a report for cash flow in & units my end date shows as sept 2019.My planned dates of resource & activity are not same. I want to know what could be the possible reason & how to resolve this problem

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Joe,

    First of all, welcome to Planning Planet!!!

    The reason why you get 2019 end date it is because of your resource planned finish date. To resolve your problem try to go to "Assignments’ located at the left corner of your screen and show the start & finish dates.

    Now try to trace those 2019 end dates and others then change it the same dates to your activities.

    Try this exercise and see what happen.

    Hope this helps.

    Regards,

    Arnold