Expenses in financial periods (P6)

Valerii ButurlakinMember for 17 years 4 months
Created
3
1
0
Hi!

How I can see expenses in financial periods using reports?

Best Regards,

Valerii

3 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Valerii

    I have moved your thread to the P6 forum.

    You will get a better response from here.

    Best rgards

    Mike Testro
  2. 0
    Andrew Podolny ·
    Hi Valerii.
    Use Report:
    Activity Past Period Actuals
    From columns add the folowing:
    Actual Expense Cost.

    Regards,
    Andrew
  3. 0
    Valerii Buturlakin ·
    thank you, Andrey.

    May be do you know, if actual expenses costs of financial period save in DB?

    Best regards,

    Valerii