Vertical Lines on Bar

Izam ZakariaMember for 20 years 4 months
Created
1
2
0
Guys,

Once I tried to collapse all the project bar schedule (from level 3 to level 2), the vertical lines were exist on that existing bar. How do I want to remove it?

Thx

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Izam,

    Go to View --> Bars, under the name column select the display bar. Try to play on it by using the "Shift up" & "Shift down" and select apply. Try to notice the changes.

    HTH.

    Regards,

    Arnold