Earn value Question

Brian YungMember for 17 years 7 months
Created
1
1
0
Gentlemen,

I would like to know when I update my schedule, in the resource section,and fill out the Actual units, Do I enter the erned value or the Actual spent ?

Thanks,

Brian

1 reply

Oldest first
  1. 0
    Niles Luo ·
    hi,
    I think it is necessary to fill Actual spend in order to calculate the EV. EV is calculated according to the baseline.
    Regards,
    niles