Spending plan
In the Open Standard
Rohit RangnekarMember for 17 years 4 months
- Created
- 2
- 1
0
Dear All,
Previously I have asked about spending plan and spending tally and it was told that spending plan is plan cost of parent WBS while spending plan tally is plan cost of child WBS under main WBS.
Now I have parent WBS whose plan cost is 100 which has come from child WBS as 80+20.Where/how I can mention these 80+20 in spending plan tally?
Regards,
Previously I have asked about spending plan and spending tally and it was told that spending plan is plan cost of parent WBS while spending plan tally is plan cost of child WBS under main WBS.
Now I have parent WBS whose plan cost is 100 which has come from child WBS as 80+20.Where/how I can mention these 80+20 in spending plan tally?
Regards,
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?