EV report

Rohit RangnekarMember for 17 years 4 months
Created
1
1
0
Dear All,

I am watching a report by name : “ WBS earned value definition list” in which certain fields are there with values , like EV % completion factor = 4 , EV ETC technique = Total remaining cost and EV performance factor = 0.88 . What these fields stands for and the use of values in them ?

Regards,

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Rohit,

    These are the techniques for computing performance % complete & for computing estimate to complete.

    Try to change the custom % complete and see what happen. Show the ETC in your column and change the performance factor.

    Regards,

    Arnold