Adding Sub Projects to a Project in P6

Nithin ShettyMember for 22 years 1 month
Created
3
4
0
Dear All,

Can anyone kindly guide me how to add Project - Sub Project environment in P6.

To be specific, I am preparing a Baseline Program for a 5 towers project. As the number of activities for each tower is more than 20000, I am planning to have a Sub Program for each tower, then combine to a main Program.

Please guide me step by step procedure to have Project - Sub Projects in P6.

Thanks in advance.

Nitin

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Nithin,

    You can create sub-project by using WBS or by EPS.

    Regards,

    Arnold
  2. 0
    Nithin Shetty ·
    Thanks Arnold.

    But can I link activities in the different projects in the EPS. How? Please explain.
  3. 0
    Ahmet KILIC ·
    There is a way to link activities even if they belong to different projects.

    On `Assign Predecessors/Successors` windows you should click on "Display: All Activites" and choose ’Select Project’ command. The EPS system will show up, and then you may choose the project containing the activities that you will create a link to.

    Regards,
    Ahmet