Adding Sub Projects to a Project in P6

Nithin ShettyMember for 22 years 1 month
Created
1
3
0
Dear All,

Can anyone kindly guide me how to add Project - Sub Project environment in P6.

To be specific, I am preparing a Baseline Program for a 5 towers project. As the number of activities for each tower is more than 20000, I am planning to have a Sub Program for each tower, then combine to a main Program.

Please guide me step by step procedure to have Project - Sub Projects in P6.

Thanks in advance.

Nitin

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Nithin,

    You create sub-project by WBS or by EPS.

    Regards,

    Arnold