Project End dates Changes when Importing

Amreshwar ShuklaMember for 23 years 5 months
Created
3
5
0
Dear All,

I have strange problem while importing the contractors program !

It gives the correct dates when I am importing on the server based database but gives the 3 days duration less, when I am importing on the laptop. If everything is same (same .xer file, same scheduling parameters ) then why is difference in the dates?

Is it due to database structure or I am missing something?


I am using P 6.0 at server and P6.01 version at laptop.


Thanks to all responders in advance.

Regards,

A.S.Shukla

3 replies

Oldest first
  1. 0
    Muhammad Anwar ·
    Amreshwar,


    The default setting in the import configuration option is keeping the existing calendars. It means if you have calendar with the same name as you are importing with XER then import will keep the existing calendar. what you need to do is to change the import configuration option for calendars to ’update existing’

    Hope this will solve the problem.

    regards

    Muhammad
  2. 0
    Amreshwar Shukla ·
    Dear Muhammad,
    Thanks for the reply,
    I have change the import configuration to the ’update existing" but no difference.

    I think this may be due to some other setting , which I am not able to figure out this moment!!! May be due to different versions??????

    Can any body help on this issue>>

    Thanks.
  3. 0
    Dieter Wambach ·
    Amreshwar

    Did you check the hours per day settings in the Admin preferences?

    BTW if you have a maintenance contract it’s better to upgrade. Some bugs of version P6.0 (pre Oracle) became solved in P6.1.

    Regards
    Dieter