How to Put Target 1 & Target 2 in P6 Just like in P3

Florante IletoMember for 19 years 11 months
Created
4
3
0
Guys,

How can we put Target 1 and Target 2 in P6 just like in P3?

In P3 I use Target 1 Start/Finish date to compare with the actual start and Finish date. While in Target 2, I usually use it to compare the Planned % Comp with the Actual % Comp.

Thanks in advance

4 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Florante,

    With P6, you don’t need to create a Target 2 schedule because, there is already available Schedule % Complete, when you assign a Target 1 schedule.

    Regards,

    Arnold
  2. 0
    A D ·
    Go To Project -> Maintain Baseline for adding all baselines

    and then Go To Project -> Assign Baseline to add, User, Primary, Secondary or tertiary baselines.

    Cheers,
  3. 0
    R. Catalan ·
    Hi Florante,

    Arnold is right.

    Assuming that you’ve already assigned a baseline on your programme, this is the simple steps to display them:

    1) Click View then Columns

    2) Expand Dates option, then select to display the following:
    - BL Project Start
    - BL Project Finish
    - Start
    - Finish

    3) Expand Percent Complete, then select to display the following:
    - Schedule % Complete
    - Activity % Complete

    4) For Variance Analysis (Finish Dates / Duration), expand Duration, then select to display the following:
    - Variance - BL Project Finish Date

    5) Create a UDF and do Global Change for Variance % Complete

    Best regards,
    R. Catalan
  4. 0
    Florante Ileto ·
    Is the Schedule % Complete equal to Planned % Comp in P3?
    In P3 to get the Planned % Comp, I usually press CNTL F9, DATA DATE same as in the update.

    In P3, when you assign target 1 and target 2, the column description will show, say, target 1 early start, target 2 early start, etc. In P6, I assign primary, secondary, but I cannot distinguish which is which

    To put in in tabular form :

    P3 vs P6
    Update File Update File
    Target 1 BL or BL1 or primary?
    Target 2 BL1 or BL2 or secondary?
    % Comp(For Update File) Activity % Comp?
    % Comp (For Target 2) Schedule % Comp?
    Target 1 Early Start BL Project Start?
    Target 2 Early Start BL 1 Early Start?

    To get Planned % Comp?

    In P3-CNTRL F9 + CURRENT DATA DATE,

    In P6 ?

    Thanks again

Log in or join to reply