P6 UPDATION

Arun VasanthMember for 17 years
Created
3
2
0
Dear friends Iam very new in P6 ..
Before I was using p3.In P3 it is very easy to update the progress.Make a copy of the base line and make Base line as target & update the progress.In manual updation we will get the actual progress & by automatic updation we will get the planned progress which we can use in the monthly progress report Planned Vs Actual.
Now dear friends how I can do these things in P6.Iam very much confused....

With regards
Arun.V

3 replies

Oldest first
  1. 0
    A D ·
    make a copy of the baseline first.\

    Go to Project -> maintain baseline and add baseline to be added to the current project.

    Then go to Project -> Assign baseline and then select the primary or user baseline.

    To update program automatiucally, use spotlight tool.

    To update baseline, go to project -> maintain baseline and then click update baseline button on the right hand side.

    Cheers,
  2. 0
    A D ·
    Hi Arun,

    U can find the P6 manuals here for reference.

    http://ftp.primavera.com/docs/6.1/
  3. 0
    Arun Vasanth ·
    Thnxs Raviraj..
    Thnxs Planning planet...

    Arun.V