Import & Export

Arun VasanthMember for 17 years
Created
9
2
0
Dear friends
Now I hear with the topic import & export to excel in P6.
In primavera it was very easy ..Only selected activities we can export to excel & return back after workouts.
In the case of P6
1.At the time of exporting all activities are exporting ....
2. Two sheets are comming while exporting /

Is there any way to export the activities same like P3
for eg Block work & Plaster activities only

With regards
Arun.V

9 replies

Oldest first
  1. 0
    Neal Walsh ·
    Arun,

    I think this is what you’re after, and It’s very easy, just run a filter on the activities you want to keep, then highlight them and copy.......open Excel and paste, you can remove anything you don’t want later.

    Walshy
  2. 0
    Arun Vasanth ·
    Thnxs Washly

    No need to export ???? hw we will import to P6??

    With regards
    Arun.V
  3. 0
    Mk Tse ·
    On export wizard, when screen for item selection prompt, there are 3 tab pages on this window, one is item selection, one for filter and one for sorting order. Input your selection criteria on Filter page
  4. 0
    Neal Walsh ·
    Nope, no need to export Arun....

    BUT.....importing INTO P6 is slightly different, and can be somewhat awkward....

    What I have done in the past is to export from P6 into Excel, purely to give me the layout and the specific formatting that Primavera understands. For example, once exported into Excel, you will notice the headings:

    task_code status_code wbs_id wbs_name task_name end_date start_date delete_record_flag

    Also note that each of the Cells contain ’ prior to the info. Have a play around with this, pasting the correct info into the columns with the headings as described above.

    I also believe there may be an easier (and less time consuming) way of doing the import with the SDK tools. I’m pretty sure Arnie mentioned something about it a while back so maybe he can chip in and shed some light on the matter. But for now, try the above method, I have definitely got it to work before, and as I said...it can be a bit touch and go.

    Good luck

    walshy
  5. 0
    Arnold Puy ·
    Hi Arun,

    There are several ways on how to export or modify your works in Excel.

    1. In Activity Window you can simply right click anywhere in the activity table area and select "Export to Excel"
    2. In the File Menu --> Export.
    3. By using the Primavera utilities (e.g. Dictionary6x.xls, Activity6x.xls, Project6.xls, etc..) with the help of SDK.
    4. Copy & Paste to Excel.

    The #1 functionality is limited, easy and only available in the Activities Window.

    In your case, you can use the #1 however, it is depend in your needs. Display all the required Columns (i.e. Activity ID, Activity Name, Original Duration, etc…) and create a new filter using the below parameters.

    (Any of the following)
    Where: Activity Name "contains" or "starts with" block
    Or: Activity Name "contains" or "starts with" plaster

    When done, you can now proceed to step #1. Otherwise, you can go for step #2 and then import it back to P6 by selecting File --> Menu --> Import.

    Regards,

    Arnold
  6. 0
    Arun Vasanth ·
    Hai Arnold
    Still Iam facing the same problem .While exporting instead of predessor name I can see only predessor & Successor ID which is really confusing for me ....

    Please help Arnold .
    With regards
    ’Arun.V
  7. 0
    Arnold Puy ·
    Hi Arun,

    As I mentioned in my previous post step #1 is only limited. Proceed to step #2.

    Go to File Menu --> Export --> Spreadsheet - (XLS), in Export Type, select Activity Relationship, then add a new Template, you can see the Predecessor and Successor Activity Name.

    Regards,

    Arnold
  8. 0
    Arun Vasanth ·
    Thnxs Mycal

    It was wounderfulllll


    With regards
    Arun.V
  9. 0
    Mk Tse ·
    can select "Activity detail" and "relationship" at the same time. if both option checked, the template will be served for both