Sample Project

Jatinder KUMARMember for 16 years 7 months
Created
2
3
0
when I installed P6 on my laptop,I installed it without sample project.Now I need sample project..any website from where I can download sample project in my P6???

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Kumar,
    why don’t you reinstall P6 with the sample projects?
    Alexandre
  2. 0
    Muhammad Anwar ·
    Jatinder,


    Put the cd1 in and explore it instead of autrun.
    open install/database/configAsst
    it will open database wizard
    select
    create new primavera database
    and put key EC C01 in and hit next.
    Select
    Microsoft Sql server[if not oracle database]
    and check to include sample project data
    Hit next
    Select
    PMDB database and hit next
    Select
    Load application data only and check to load license key
    hit folder icon to direct to license file.
    and hit next on warning screen.
    Then enter
    username: privuser and
    Password: privuser [if you are on defaults]
    server Name: localhost\primavera
    database Name: pmdb$primavera
    hit next and select
    Yes, I want to overright my databse with dafault data and
    hit next.
    if every thing was put right then it should update the database with sample projects.
    But be aware it will overwrite the existing database. so you need to backup if you have some projects in the database to save.
    Regards

    Muhammad