cross project links in P6v7
In the Open Standard
Gün GöksuMember for 21 years 6 months
- Created
- 0
- 3
0
Hello,
I have copied a group of activities from a project to another.
some activities where available on both projects.
How do I change the wbs on the Predesessor and Sucessor to point to the current project?
I couldnt do it with exports. somehow P6v7 refuses to acnowledge these links in exports.
Thank you in advance.
Goksu
I have copied a group of activities from a project to another.
some activities where available on both projects.
How do I change the wbs on the Predesessor and Sucessor to point to the current project?
I couldnt do it with exports. somehow P6v7 refuses to acnowledge these links in exports.
Thank you in advance.
Goksu
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?