Assigning Weightage in P6

Soumen MandalMember for 17 years 8 months
Created
1
1
0
Can anybody please help me in assigning weightage to the activities in P6. I will require this to measure the progress achieved for the project

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Saumen,

    Please read this forum (click link below). I mentioned three Option of assigning weightage to the activities using duration if cost is not available.

    Duration Percentage Complete Post # 3

Log in or join to reply