Price / Unit allocation in Roles........
In the Open Standard
Haresh JayanthMember for 20 years 1 month
- Created
- 1
- 2
0
1) If we are creating more than one price / unit in roles in P6, how to assign other prices , when we are adding roles to an activity.
For example i have create price/ unit 100, 175 & 250. But when i add a role to an activity , it is taking my first price i.e. 100 only, i dont have an option of selecting other prices...
2) Why does my Budget cost comes zero , even if i have a role with price / unit as $ 100 /h with Budgeted units of 7d. But still my budgeted cost is 0. How is it possible...
Can anyone clarify the above query?
For example i have create price/ unit 100, 175 & 250. But when i add a role to an activity , it is taking my first price i.e. 100 only, i dont have an option of selecting other prices...
2) Why does my Budget cost comes zero , even if i have a role with price / unit as $ 100 /h with Budgeted units of 7d. But still my budgeted cost is 0. How is it possible...
Can anyone clarify the above query?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?