Estimate at completion

Dinesh Kumar DamavarapuMember for 24 years 7 months
Created
3
3
0
Dear All,

I have an issue with the estimate at completion, this is not the same as earned value at the data date. Why is that? and how could I make that equal.

Thanks & regards

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Dinesh,
    EV = Physical Progress x BAC
    EAC = Actual + Forecast to complete

    Of course that is not the same.
  2. 0
    Dinesh Kumar Damavarapu ·
    Rodel,

    Thank you for your reply.

    I understand the formula but before the data date these figures should be equal. Forecast is for the future not for the past.

    Basically, my problem is that I am trying to generate a cash flow curve for the future taking account of the existing actuals ( my actual and EV is the same). What is your suggestion. What are the figure I should be using, is it remaining cost, estimate at completion?

    Thanks & regards
  3. 0
    Rodel Marasigan ·
    Dinesh,
    Remaining Cost start from datadate onwards should be the same as Estimate At Completion from datadate onwards.
    If your EV = AV then EAC should be the same as AV + ETC (estimate to complete or remaining)
    Can you clarify what do you mean by EV is not equal to EAC?