Thresholds Limits

Haresh JayanthMember for 20 years 1 month
Created
1
3
0
Hi,

I have set a thresholds, total float with lower limit 0d and upper limit 20d. When i calculate the thresholds the activities, which has thresholds more than 20d is also generated?

Why so? Since i have set a limit, why activities , which is going beyond my limit is also seen....

Can anybody guide me...

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Threshold parameter (lower limit and upper limit) doesn’t control the program. I will not constrain any field selected (i.e. total float). The purpose of parameter is to instruct P6 when issue need to be generated.
    Ex: As per sample above = total float 0 to 20 limit means that when threshold are being monitor/ calculated and the total float exceeded below or equal to the lower threshold or equal to or above the upper threshold value or parameter then an Threshold issue will automatically generated. Any issues generated by threshold cannot be edited on the detail tab.