Import activity code values and descriptions from excel

Roozbeh TaheriMember for 23 years 5 months
Created
3
3
0
I have prepared a list of activity code values and descriptions for an activity code in excel.

I want to import them into P6.1 and assign them to activities.

Is it possible to import activity code values and descriptions from excel into primacera P6.1

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    If you have excel SDK (Dictionary.xls) yes you can import activity code and description (global or project)
  2. 0
    Joyjit Mishra ·
    I am also having the same problem.

    I would be thankful if i could get the step by step. Already I have installed the SDK version in my machine.

    I am unable to find the Dictionary.xls .

    Please guide.

  3. 0
    Rodel Marasigan ·
    Joyjit,
    Dictionary.xls is normally found on Primavera installation CD and it is not included when you install SDK.