Project with different Portion completion dates
In the Open Standard
kannan KGMember for 17 years 8 months
- Created
- 4
- 2
0
I have one project with with 5 portions, each portions has different completion date (ex. portion 2 finish after 60 days of portion 1 finish) and LD.
When making schedule the portion 5 only showing in critical path.
How to show critical path for each portions in single schedule.
When making schedule the portion 5 only showing in critical path.
How to show critical path for each portions in single schedule.