import data from p3.1 to p6.2 !!!!!!

Mai TawfeqMember for 16 years 7 months
Created
5
1
0
Hi dears :

Am trying to import data from p3.1 to p6.2 , the importing always is completed successful , but when I open the project , it comes without WBS , I have tried many times and always come in same result , can anyone tell me the reason beyond it …………!!!!????.

Maiiiiiiiiiii

5 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Mai,
    I P3.1 WBS is not compulsory and most of the time using Activity Code instead of WBS. In P6 WBS is some sort of compulsory and encourage P6 user to use WBS. Check P3 files first in P3 program and organize by WBS. If no WBS define and assigned then no WBS will be imported to P6.
  2. 0
    Mai Tawfeq ·
    Dear Rodel :

    Am the one who did the programme in p3.1 and I define WBS , I have not use activity codes ,all the activities is organized into WBS .
    So what do u think the reason can be now ?

    mai
  3. 0
    Rodel Marasigan ·
    Mai,
    If you define WBS then the problem is the way you import it. When importing P3.x and reached to Update Project Options click Modify and check what is selected under Action. It should be Update Existing or Insert New and not Do not Import.
  4. 0
    Mai Tawfeq ·
    Dear Rodel I solve the problem:

    The issue was in (advance option I select import unused WBS cods ), waooooooooooooooo.

    mai

  5. 0
    Rodel Marasigan ·
    Mai,
    Congratulations!!! but you haven’t mention that you haven’t assigned created WBS??? which is another issue otherwise I direct you to correct solutions. (:

Log in or join to reply