Hi,

We have in Report Wizard , "Configure selected subject area" in that we have option to use the tick mark "Hide the subject area" , can anyone explain we is the meaning of this option...

regards,

Haresh Jayanth

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Haresh,
    If you run Report Wizard and selected multiple additional subject area you turn off and on the additional subject area if needed by marking Hide the subject area on each additional subject area selected.

    Note: If only main subject area is present ticking "Hide the subject area" is useless otherwise nothing to report.