Print Resource Availability
In the Open Standard
Rafael DavilaMember for 22 years 7 months
- Created
- 58
- 11
0
Resource Availability (Production) Tables
Availability of resources can vary with time, the basic availability definition is done at the resource tables, and here fixed calendar variations can be defined. But fixed variations is not always good modeling, at times you need the availability to move with a group of activities and then lower availability should be defined in order to avoid unnecessary idle resources and correct resource allocation based on variable availability. Good software provides for the scheduler be able to modify resource availability through activities that move as the schedule moves with time.
In P6 how can we print resource availability tables for:
1)Resource availability defined under resources tables?
2)Resource availability defined at the activity level?
3)Combined resource availability?
Please provide some means that can be practical when using hundreds of resources as use of histograms is kind of useless when dealing large jobs.
How P6 Digger handles changes in resource availability?
Best Regards,
Rafael
Availability of resources can vary with time, the basic availability definition is done at the resource tables, and here fixed calendar variations can be defined. But fixed variations is not always good modeling, at times you need the availability to move with a group of activities and then lower availability should be defined in order to avoid unnecessary idle resources and correct resource allocation based on variable availability. Good software provides for the scheduler be able to modify resource availability through activities that move as the schedule moves with time.
In P6 how can we print resource availability tables for:
1)Resource availability defined under resources tables?
2)Resource availability defined at the activity level?
3)Combined resource availability?
Please provide some means that can be practical when using hundreds of resources as use of histograms is kind of useless when dealing large jobs.
How P6 Digger handles changes in resource availability?
Best Regards,
Rafael
58 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?