Dear friends
Please guide me to find the monhly percentage by each activity in p6


With regards
Arun.V

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Arun,
    Monthly planned percentage is only available if expenses or resources is assigned to activity even on a summary level only.