resorce assignnment effective date
In the Open Standard
Kumar SMember for 16 years 8 months
- Created
- 2
0
Dear All,
can you guide me for the below mentioned query..
i have assigned the resources of the last year(2008)project.
since the limit (max units/time) for the last project is set for ex.60h/h.
now dor the present project i hace to change it to 40h/h.
now i have 2 options .
either i can edit the limit in the already available units(whose effective date is jan 2008.
the other option is i can add one more unit and set the limit(with effcetive date as july2010)
so now when i level the resources p6 will take how many resources as available.
ie it will consider only the resorces of 2010 (with 40h/h)or it will take 2008 resources also(60h/h).
i think my question is clear.
thank you.....
can you guide me for the below mentioned query..
i have assigned the resources of the last year(2008)project.
since the limit (max units/time) for the last project is set for ex.60h/h.
now dor the present project i hace to change it to 40h/h.
now i have 2 options .
either i can edit the limit in the already available units(whose effective date is jan 2008.
the other option is i can add one more unit and set the limit(with effcetive date as july2010)
so now when i level the resources p6 will take how many resources as available.
ie it will consider only the resorces of 2010 (with 40h/h)or it will take 2008 resources also(60h/h).
i think my question is clear.
thank you.....
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?