How to show Overall Percentage Complated ?

Irfan KhanMember for 17 years 3 months
Created
1
2
0
Hi to all,

While updating my schedule i notice that on Total Bar Everything is showing except overall percentage. I mean to say i want to show my schedule Percentage, like Primavera P3.

thanks,,,,,,,

1 reply

Oldest first
  1. 0
    Duy Pham ·
    HI,

    Your schedule need to be cost loaded to be able to display % complete at summary band (by using performance % complete)

    You can search lots of topics about this subject here on planning planet especially from Mr. Rodel Marasigan.