Spending plan

Alexandre Faulx-BrioleMember for 23 years 8 months
Created
5
1
0
Hello P6 experts,
is it possible to reset the Spending Plan and Benefit Plan entries in the Project Detail form, Spending Plan tab to Zero?
when I enter a new value, it is added to the existing one, e.g. 170 + 1 = 171, 170 + 0 = 170
I have already set to Zero all the values at the wbs level.
Thanks for your help,
Alexandre

5 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Alexandre,
    Spending Plan and Benefit Plan entries are available from EPS, Projects up to WBS. You should be able to remove the entries each month. You have to check from EPS -> Project to WBS of which entries have value to zero out.
  2. 0
    Alexandre Faulx-Briole ·
    Hi Rodel,
    I have put every WBS level to Zero already; on the WBS screen, Spending Plan tab, every WBS level reads Zero but at the project level on the same screen I cannot put the monthly values to Zero
    Alexandre
  3. 0
    Rodel Marasigan ·
    Alexandre,
    You have to check the Project Detail Tab-> Spending plan if any value is assigned. If Project level is selected and Spending Plan tally has value then the value is on WBS but if the spending plan has value then it is on Project level. The faster way to check is showing the column of Spending Plan and Spending Plan Tally at WBS window.
  4. 0
    Alexandre Faulx-Briole ·
    Rodel,
    Spending Plan Tally values are all zero; Spending Plan montly values for the project duration are aboce zero and I cannot put them to zero; same for benefit.
    Orignila budget is also zero
    Alexandre
  5. 0
    Alexandre Faulx-Briole ·
    Rodel,
    as I was not able to set the values back to zero, I have exported the project as a MSP XML file, then re-imported it and replaced the original project with the imported file; and that’s it: the offending Spending / Benefit Plan are set to zero
    Thanks anyway for your help,
    Alexandre

Log in or join to reply