night shift activites

Kumar SMember for 16 years 8 months
Created
3
1
0
dear all

how to filter the actiivtes which is scheduled only in the night shift.
i have taken the calendar as 24/7.
so now i have to assign the activites which is starting in the night shift to the night supervisor.
what is the parameter in the filter to be selected.

thank you.


3 replies

Oldest first
  1. 0
    Kumar S ·
    Dear all


    can anybody reply to my query please..


    thank you..
  2. 0
    Rashid Iqbal ·
    Kumar,

    It appears that you are working for a TA project..

    Sometimes the scope is well defined for the night shift and at times the night shift just assist the day shift by completing the work in progres etc.

    If it is the first case then there would be a code for night shift or night shift supervisor. Check it first...Thanks.

    R
  3. 0
    Wayeez Ahmed ·

    night shift activities

    Hi Kumar,

     

    If the night shift activities are clearly defined just create a calender as Night shift and assign that calender to the NS act.

    then filter by calender. Its very simple.

     

     

    thanks

     

    W.A Shariff 