Multi-Resources in Report
In the Open Standard
Vaughn EdwardsMember for 18 years 5 months
- Created
- 1
- 1
0
If I run a report to view all my project resource budgeted hours everything shows up. In another report I created to show budgeted hours, earned hours, at completion, and scheduled % complete and then set my filter to show all resources I need, not all the resource hours show up. Looks like those avtivities that have multi resources assigned to them don't add up in the second report. Any suggestions?????
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?