Excel Export & Import Issues

Shah. HBMember for 17 years 10 months
Created
2
1
0

Hi to all

 

I exported a program P6 in XL format to workout resources,when i imported back to primavera ,it displayed 'system is running out of memory ,close other applications and carry the operation again '

Is there any solution to fix the problem

 

2 replies

Oldest first
  1. 0
    Ronald Winter ·

    Shahul,   The simple solution

    Shahul,

     

    The simple solution is to e-boot your computer, do not run any other programs except for P6, and then try to import it again.  Over time, computer memory ‘gets lost’ and a re-boot will cure the problem.  Good luck!

  2. 0
    Shah. HB ·

    Hi Winter I did the same you

    Hi Winter

     

    I did the same you advised  but still the problem exist