Import WBS Code in P6

Gokulakrishnan GanesanMember for 16 years 4 months
Created
4
2
0

Hi everybody.. Can any one of you tell me that is it possible to import WBS Code from Excel to P6. Since we are working in WBS in 2 different system for the same programme, We want to import the data from one system to another.. We have tried by exporting the WBS code, WBS name and WBS path and import that to another system.. Afetr the completion of importing data there is no change in the WBS for activities..

4 replies

Oldest first
  1. 0
    Prabin Kumar ·

    I am doing this by this

    I am doing this by this way...

    If u r trying to copy another plan WBS structure to ur plan, I suggest open both plan altogether and copy the desired WBS under ur plan  node (remember...if u want to copy the structure only, please uncheck the activity while copying otherwise activities will also be copied to ur project) , close all file and open ur plan only.  Now u can shift ur activities under copied WBS simply by Cntr'X' & Cntrl 'V' 

    or if u trying to change the WBS by Export and import first export your schedule in excel selecting Activity ID and WBS Code under Export Type 'Activities' , then open and change the individual activites WBS code in excel and import to P6 again...but pl remember that in this case u shud hv the desired WBS structure defined in ur project ...if u hv not done this...u can do it by first method

    Thanks,

  2. 0
    Jeoffrey Reyes ·

    If you know how to use SDK

    If you know how to use SDK you can do it also by simply putting your WBS structure. All you need to do is to prepare your PARENT WBS ID, WBS CODE and WBS NAME. Then just set your WBS from your Macro then it will go through your P6 program.

     

    Cheers, 

  3. 0
    Michael Lepage ·

    HiMy colleague has released a

    Hi

    My colleague has released a step-by-step tutorial on using the SDK to import WBS.  Please have a look.

    https://www.planacademy.com/how-to-import-wbs-from-excel-to-primavera-p6-using-the-sdk/

     

    Happy Planning!

     

    M

  4. 0
    Zoltan Palffy ·

    in the project that you want

    in the project that you want to copy the wbs strucutre to make sure that there is NO wbs structure other than the very top level which is automatically Project ID

    open both projects

    got to the wbs directory 

    summarize and roll up both projects 

    go to the project where the wbs exists

    right click and select copy 

    highlight the other project and select paste

    you will be given several options choose wbs only

     

    BTW

    when you tried to import before did change the first few characters of the wbs to match the other Project ID name ?

     

Log in or join to reply