Staffing plan in P6

Carmen ArapeMember for 22 years 3 months
Created
4
2
0

 Dear Planners,

 I need to create a staffing plan by discipline. The staffing plan needs to be based on heads (name+lastname), for instance:

                        (manhours)

Civil                 wk1      wk2      wk3

Eng.1              40        20        20

Tec 1               40        40        40       

Tec 2               20        10        10

 

I have loaded my schedule with budgeted units per activity at the level of one resource, for instance civil (670 hrs).

 Is there a way in P6 to convert my budgeted units per activity into people (by name) per discipline.

The staffing plan is normally done in Excel.

Due to my manhours (budget) are already in P6, I would like to have the same source of manhours.

 

Any planner in the world with the same thought ???

Cheers,

Carmen

 

 

4 replies

Oldest first
  1. 0
    Juan Carlos Córdoba ·

    Hello Carmen: imagen1.jpg

    Hello Carmen:

  2. 0
    Juan Carlos Córdoba ·

    After that copy and paste in

    After that copy and paste in Excel (Después copias y pegas en Exce)l:

    And finally format the graphic (Y después ordenas y formateas el gráfico):

  3. 0
    Zoltan Palffy ·

    yes you can add roles and use

    yes you can add roles and use peoples names in the roles

    go to enterprise roles and set them up there then assign the resource AND THE ROLE

  4. 0
    Rafael Davila ·

    So easy if using automatic

    So easy if using automatic skill replacement.