Skip to content

data not coming through on import

Simon HegartyMember for 22 years 3 months
Created
1
2
0

 

 

I have an issue whereby upon mporting a contractors programme into our p3e it is ignoring the role dates assigned to an activity

 

for example a activity has 1 resource attached with a finish date 13th Dec 2010 and 3 Roles attached with a finish date of 31st Jan 2011 (all driving the activity dates) however the activity finish date is 13th dec.

 

I have the text file which accompanies the xer sent from the contractor and this confirms that the finush date on the activity should be 31st Jan

 

im am using p3e version 5.0  - the contractors programme is also version 5.0

 

any suggestions?

 

Thanks

1 reply

Oldest first
  1. 0
    Dieter Wambach ·

    Hi Simon Just an assumption:

    Hi Simon

    Just an assumption: With the import you create a new project. Then some parameters for this new project are taken from the default project.

    I would check if "drive activity dates by default" is unmarked - view Projects --> Resources. If not unmark and for the activities as well - view "Assignments".

    Good luck!

    Dieter

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?