How do you mergre 2 different projects into one project?

Ruel CamaquinMember for 17 years 11 months
Created
4
3
0

Guys,

So how do we merge 2 or more different project in a single project in P6? resourcing, cost account and other details will be encoded after the projects were merge.

Thanks in advance PP!

Ruel

4 replies

Oldest first
  1. 0
    Dieter Wambach ·

    Ruel   You can open two or

    Ruel

     

    You can open two or more projects in common and P6 will regard them as one project.

    Do you want to merge them "forever" or just for a session?

    - "Forever": View "WBS" --> Open all projects --> Move all WBS into one project. That's it.

    - Temporarily: Leave all projects untouched --> Just open in common.

       Watch Schedule parameter setting "Calculate float based on end date of:" - Not essential, but will help.

     I hope this will solve your item.

    Regards

    Dieter

  2. 0
    Ruel Camaquin ·

    Dieter, Thanks for the tip,

    Dieter,

    Thanks for the tip, it gonna be forever. In order to save what i have done before i've made a reflection of the projects i wanted to merge - it's better to be safe than never.

    Thank you very much!

    Ruel

  3. 0
    Arun Kumar ·

    Thank you Mr. Dieter.

    Thank you Mr. Dieter.  

  4. 0
    Zoltan Palffy ·

    another way to do it is to

    another way to do it is to open one project and have the other project as an xer file. Select file import and during the importing undeer the IMPORT ACTION change this option and select 

    ADD INTO EXISTING PROJECT instead ofthe default setting cretae new project 