P6 R8 Summarisation issues
- Created
- 5
- 2
Eventually we have managed to get version 8 up and running both on client and web i.e. P6 Professional and P6 EPPM. It appears to be running smoothly at the moment. One of the issues I have found, is that when we have summarised all the projects, when we open up P6 Professional (which is what we use primarily) summarised data is not shown and you need to press F5 to refresh the database. In the previous versions, as soon as the database was opened it automatically showed summarised data. Have I missed a tick box somewhere or do we have to live with it or have Oracle got an enhancement in the pipeline.
Regards
Roger
5 replies
Oldest firstLog in or join to reply