Budgeted Units Import&Export

Erdem EminolMember for 19 years 7 months
Created
2
0

Hi,

I want to modify budgeted units. I export existing units to excel and modify it on excel, then import to P6.1.

Nothing is changed. I checked currency what I mean decimal and grouping part. It is suited to excel.

Do you have any idea what the reason is? Thank you.

Regards,

Erdem

2 replies

Oldest first
  1. 0
    Andy Power ·

    Did you export the current

    Did you export the current budgeted units to Excel via the export to xls function?  If so as long as you only change the data and not the structure of the file (headings, tab names) then this should work.  Your other option is to do the same but using the SDK.

  2. 0
    Erdem Eminol ·

    I only change budgeted unit

    I only change budgeted unit data using p6 excel spreadsheet template; however it is not changed.