Skip to content

Use of Differnt Calenders P6

Jeffrey NewmanMember for 21 years 2 months
Created
2
3
0

Hi All,

I wonder if you can help using p6.7, have put together schedule but have used two different calenders within the schedule. One calender a Ten day fortnight 9 hr working time the other 7 day calender working 12 hr days.

 

On the activities using 7 day calender if I put a duration 0f say 19 days for an activity the start and finish dates show a duration of 13 days. I have checked correct calender assigned to correct activity but it still comes out with the same result!

 

Can anyone throw some light on why this is happening Cheers!

2 replies

Oldest first
  1. 0
    Kumar S ·

    Dear Newman, Refer the below

  2. 0
    Mike Testro ·

    Hi Jeffrey Check the

    Hi Jeffrey

    Check the calendars allocated to your resources.

    Best regards

    Mike T.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?