Locking a project in P6?

Chris HibberdMember for 20 years 6 months
Created
1
3
0

Hi guys,

I'm wondering if anyone has come across a method of locking a project in P6 to prevent users of the enterprise from making changes to it?

I have admin superuser access and can change the permissions of the other users if necessary. I need them to retain full functionality for editing and developing programmes in the remainder of the EPS but have read only access to one particular EPS leg.

Any advice is appreciated.

Many thanks

Chris

1 reply

Oldest first
  1. 0
    Daniel Limson ·

    HI Chris, Under Admin, click

    HI Chris,

    Under Admin, click security profile and set up access rights. You may need additional coding structure for OBS as mentioned by Alain.

    Cheers,

    Daniel