Create user accounts

Paul CarronMember for 15 years 4 months
Created
2
2
0

Hi All,

 

Are there any documents that describe how to add a user in Primavera?

 

Regards

Paul

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Paul,this is an admin's

    Paul,

    this is an admin's work

    have a look at the Administrator Reference Manual, that ships with the software, page 345

    Alexandre

  2. 0
    Simon Willson ·

    Hi Paul,   You will have to

    Hi Paul,

     

    You will have to define the users global privilege, assign the user a valid license, assign the user access to the OBS, assign the user project privileges within the OBS.  If you have a database administrator, this will fall under their remit. 

     

    Regards

     

    Simon